Release Checklist for BIND 9.16.42, 9.16.42-S1, 9.18.16, 9.18.16-S1, 9.19.14
Release Schedule
Code Freeze: Wednesday, 7 June 2023
Tagging Deadline: Monday, 12 June 2023
Public Release: Wednesday, 21 June 2023
Documentation Review Links
Closed issues assigned to the milestone without a release note:
Merge requests merged into the milestone without a release note:
Merge requests merged into the milestone without a CHANGES
entry:
Release Checklist
Before the Code Freeze
-
(QA) Rebase -S editions on top of current open-source versions: git checkout bind-9.18-sub && git rebase origin/bind-9.18
-
(QA) Inform Support and Marketing of impending release (and give estimated release dates). -
(QA) Ensure there are no permanent test failures on any platform. Check public and private scheduled pipelines. -
(QA) Check Perflab to ensure there has been no unexplained drop in performance for the versions being released. -
(QA) Check whether all issues assigned to the release milestone are resolved1. -
(QA) Ensure that there are no outstanding merge requests in the private repository1 (Subscription Edition only). -
(QA) Ensure all merge requests marked for backporting have been indeed backported. -
(QA) Announce (on Mattermost) that the code freeze is in effect.
Before the Tagging Deadline
-
(QA) Ensure release notes are correct, ask Support and Marketing to check them as well. Example -
(QA) Add a release marker to CHANGES
. Examples: 9.18, 9.16 -
(QA) Add a release marker to CHANGES.SE
(Subscription Edition only). Example -
(QA) Update BIND 9 version in configure.ac
(9.18+) orversion
(9.16). -
(QA) Rebuild configure
using Autoconf ondocs.isc.org
(9.16). -
(QA) Update GitLab settings for all maintained branches to disallow merging to them: public, private -
(QA) Tag the releases in the private repository ( git tag -s -m "BIND 9.x.y" v9.x.y
).
Before the ASN Deadline (for ASN Releases) or the Public Release Date (for Regular Releases)
-
(QA) Check that the formatting is correct for HTML and PDF versions of release notes. -
(QA) Check that the formatting of the generated man pages is correct. -
(QA) Verify GitLab CI results for the tags created and sign off on the releases to be published. -
(QA) Update GitLab settings for all maintained branches to allow merging to them again: public, private -
(QA) Prepare and merge MRs resetting the release notes and updating the version string for each maintained branch: 9.16 and newer -
(QA) Announce (on Mattermost) that the code freeze is over. -
(QA) Request signatures for the tarballs, providing their location and checksums. Ask signers on Mattermost. -
(Signers) Ensure that the contents of tarballs and tags are identical. -
(Signers) Validate tarball checksums, sign tarballs, and upload signatures. -
(QA) Verify tarball signatures and check tarball checksums again: Run publish_bind.sh
on repo.isc.org to pre-publish. -
(Support) Pre-publish ASN and/or Subscription Edition tarballs so that packages can be built. -
(QA) Build and test ASN and/or Subscription Edition packages (in cloudsmith branch in private repo). Example -
(QA) Prepare the patches/
subdirectory for each security release (if applicable). -
(QA) Notify Support that the releases have been prepared. -
(Support) Send out ASNs (if applicable).
On the Day of Public Release
-
(Support) Wait for clearance from Security Officer to proceed with the public release (if applicable). -
(Support) Place tarballs in public location on FTP site. -
(Support) Publish links to downloads on ISC website. Example -
(Support) Add the new releases to the vulnerability matrix in the Knowledge Base -
(Support) Write release email to bind-announce. Example -
(Support) Write email to bind-users (if a major release). Example -
(Support) Send eligible customers updated links to the Subscription Edition (update the -S edition delivery tickets, even if those links were provided earlier via an ASN ticket). -
(Support) Update tickets in case of waiting support customers. -
(QA) Build and test any outstanding private packages in private repo. Example -
(QA) Build public RPMs. Example commit which triggers Copr builds automatically -
(SwEng) Build Debian/Ubuntu packages. -
(SwEng) Update Docker files here and make sure push is synchronized to GitHub. Docker Hub should pick it up automatically. Example -
(QA) Inform Marketing of the release. -
(Marketing) Post short note to Twitter. -
(Marketing) Update Wikipedia entry for BIND. -
(Marketing) Write blog article (if a major release). -
(QA) Ensure all new tags are annotated and signed. git show --show-signature v9.19.12
-
(QA) Push tags for the published releases to the public repository. -
(QA) Merge published release tags (non-linearly) back into the their relevant development/maintenance branches. Step 7 of the new workflow -
(QA) Sanitize confidential issues which are assigned to the current release milestone and do not describe a security vulnerability, then make them public. -
(QA) Sanitize confidential issues which are assigned to older release milestones and describe security vulnerabilities, then make them public if appropriate2. -
(QA) Update QA tools used in GitLab CI (e.g. Black, PyLint, Sphinx) by modifying the relevant <code>Dockerfile</code>. -
(QA) Run a pipeline to rebuild all images used in GitLab CI. -
(QA) Update metadata.json
with the upcoming release information.